Tuesday, December 1, 2009
"By Others" and "N.I.C."
Wednesday, November 4, 2009
Reviewing the Contractor's Application for Payment
The Architect should review even the basic information on the front page before looking at the detailed information on the continuation sheets. It helps to have a copy of the previous month's Application in hand for comparison. Once you determine that the current month's Application is for the appropriate project (seriously), check the Original Contract Sum. In more than one instance, a contractor has changed the Original Contract Sum on an Application for Payment, resulting in an increase in payment without an approved Change Order. The Original Contract Sum should remain the same for the life of the Contract. Before turning to the continuation sheets, the Architect should apply the same scrutiny to the rest of the front page calculations and the wording of the certification. Different certification language may carry different liability.
Detailed information on the continuation sheets is typically generated as part of a "pencil requisition" process and in anticipation of work to be completed by the end of the month. The Architect needs to consider whether the final Application for the month represents work that was actually accomplished by the end of the month. If the Architect is aware that an anticipated material delivery did not occur, then the Architect should not certify payment for that. Likewise, if the Architect is aware that a specific work item was not completed, then the Architect should not certifiy payment as if the item had been completed. Necessary adjustments to the continuation sheets must be carried over to the front page and to the overall amount certified by the Architect for the period covered by the Application. It may be practical for the Contractor to make the necessary adjustments and then resubmit a corrected Application for the Architect's certification. If timely payment is an overriding concern, then the Architect may need to make the adjustments by annotating the Application, certifying a reduced amount, and notifying both the Owner and the Contractor of the reasons for the adjustments. (See also It takes timely money to make a project go )
Sunday, November 1, 2009
Manage Design Costs with Early Project Overtime
This makes a lot of sense when considering a project on a compressed time line. If you're trying to figure out how to get all the work done in a short period of time, the least attractive alternative is having an army of designers and drafters burning the midnight oil and generating design questions as the completion deadline approaches. Eleventh hour overtime can quickly burn through budgeted hours and fee dollars, and too many new or unanswered questions at that stage can lead to unplanned chaos.
It's also interesting to consider how this principle of early overtime might benefit progress and labor costs on a construction site. Early trades - like earthwork, concrete, and steel - set the stage for a larger work force, and trades can multiply as the project becomes ready for their work.
Thursday, October 29, 2009
Shop Drawing Review Comments
Friday, May 22, 2009
Construction Documents Coordination Matrix
It may look a little "geeky", but this matrix can be an effective tool for considering interdisciplinary coordination needs. The design disciplines for a project are listed across the top and down one side. The intersection points represent coordination between disciplines (e.g., between Civil/Site and Electrical). Seeing the possibilities in this format can help to minimize coordination gaps. On a given project, the extent and specifics of coordination will differ from point to point, and the design displines may also differ. Still, seeing an intersection point can prompt thoughts about needed coordination between any two disciplines. For example, where Civil/Site meets Foodservice, it may bring to mind the need to coordinate the locations of exterior condensing units with site work. Etc. Etc. Etc.
Looking at this coordination matrix, it is also easy to see how extensive coordination really is (and must be) on an architectural project. On some complex projects, coordination can be seen as a full time job in itself, from the coordination of consulting agreement scopes of work to the coordination of sub-trade scopes of work and the dotting of i's and crossing of t's in construction documents.
Wednesday, May 20, 2009
Construction Documents Peer Review
A similar approach could work in utilizing the services of an independent peer review architect who can review the construction documents together with the staff who developed the documents. Compared to a "redline only" mark-up of drawings and specifications, the interactive review process can include a substantive conversation that carries longer term value for the firm, while taking advantage of review expertise outside the firm.
The 50-50 Rule
When you develop drawings - plans, sections, elevations, details, etc. - and specifications, you depend on other people to understand and make effective use of those drawings and specifications to produce desirable results. Your work must effectively communicate with others, be they other designers, consultants, owners, users, permitting authorities, estimators, bidders, contractors, subcontractors, material suppliers, and others. And the value of your work - especially technical work - is diminished by the extent that it does not effectively communicate with others.
While jobs do vary in the actual proportion of "stuff" vs. "people", a good approach to a technical job is one based on a consideration that at least 50% of the job is people related. That's the 50-50 rule.
Tuesday, May 12, 2009
Sunday, May 10, 2009
Dutchmen for a technical ground grid
Friday, May 8, 2009
The Architect's role at the construction site
An architect visiting a construction site can feel a rush of power as construction personnel approach with questions. "Finally," you may hear them exclaim, "someone with answers!" This is an opportunity to show your knowledge of construction, the project, and the construction documents, and it is also an opportunity to make a complete fool of yourself. You have to be careful to stay within the limits of your contractual role*, which is normally to observe construction for consistency with the construction documents and to communicate with the contractor's superintendent. This can be challenging when workers are gushing with excitement to hear your opinion about what should or could be done. A question may be valid and may warrant a prompt response, but the architect's reply should be consistent with the requirements of the construction documents, and it should be made through proper channels. You have to observe construction, but you should do what you can to avoid a claim or the appearance that you personally directed a worker or subcontractor to make a change. One subcontractor can sound very convincing when presenting a question or a dilemma, but there may be other factors, interests, and requirements to consider.
[*The architect's contractual role during construction is typically established by the General Conditions of the Contract such as AIA Document A-201 or by similar documents and/or amendments thereto.]
Thursday, May 7, 2009
Masonry Design: Not-Quite-Through-Wall Flashing
Wednesday, May 6, 2009
Email is Snail Mail for some
But, for some, "snail mail" still beats email. In one situation an executive who touts his company's use of computer based technology remains reluctant to make personal use of it. Sending this CEO an email message actually guarantees as much as a 2-week communication delay. His orders to his assistant - who actually receives his email - is to print it all out once every two weeks and put it into his in-box in a neat stack. He may then read it along with letters, magazines, advertisements, and other mail.
This may seem like an extreme case these days, but it illustrates the importance (and advantage) of utilizing several means of communication to deliver a message. Don't forget face to face conversation, the telephone, the postage stamp, arm waving, signing, the bullhorn, and other potentially effective ways to deliver a message. (See also Practice the Hand-off.)
Tuesday, May 5, 2009
Can you recognize a flat tire?
Specialization and automation risk some loss of practical awareness. As we come to rely more on technology and automatic systems, we can lose our internal ability to recognize a problem. The recent addition of a tire pressure monitoring system (TPMS) as a feature on automobiles exemplifies such a risk. While TPMS may signal a loss of tire pressure that is not obvious to an observer, the presence of TPMS is likely to lull a driver into thinking that it is not necessary to consider the condition of the tires before traveling. Then, if the TPMS malfunctions and does not signal the driver of a loss of tire pressure, there is a risk that the driver will continue to operate a car with an under-inflated or flat tire, possibly damaging or destroying the tire...or worse. "Hey! The TPMS didn't tell me there was a problem!" With or without TPMS, a driver needs to recognize the symptoms of a low or flat tire and to react appropriately. One of the long term effects of systems like TPMS may be TLOA (total lack of awareness).
GPS, spell-checker, and CAD (see CAD doesn't care) are other examples of helpful technologies that may, as a side effect, reduce our internal awareness of problems. In a similar way, BIM (Building Information Modeling) offers the promise of more ways to consider a building project in its formative stages, but it will still fall to the operator or viewer to recognize a problem that needs to be corrected (see What's wrong with this picture?).
Thursday, April 30, 2009
Metal Roofing Specifications: "No Visible Oil Canning" equals Mission Impossible.
I looked at the newly installed metal. It looked fine.
"Wait a while", he said. As the sky changed and the angle of the sunlight changed during the day, oil canning appeared, then disappeared, then reappeared differently. "The specs say 'no visible oil canning'," the Clerk accurately noted.
The spec writer's best intentions, possibly influenced by the designer's best intentions, were that from Day One and under any and all light conditions the metal roofing would exhibit no visible distortion. Seeing the situation in the field, a part of my mental faculties that were still intact suggested we had a problem that was more perceived than real. Over the next few days I visited and photographed a number of other projects with metal roofing - from afar, up close, and under different light conditions. These appeared to be carefully crafted installations with little or no distortion related to the installation. Yet under some light conditions and viewing angles, they all exhibited 'visible oil canning'. I put the findings into a little presentation for the client, who had been alerted to the oil canning condition by the Clerk. Following the presentation, the client was satisfied that the metal roofing was normal in terms of visible oil canning. The spec writer? Well, that's another story.
(Visit http://www.smacna.org for an October 2005 newsletter article on oil canning and information about how to minimize it.)
Construction Tolerance
Wednesday, April 29, 2009
Masonry Design: Separate hung masonry from foundation-supported masonry
In some cases the best control joint locations for wall performance will not be the best locations for aesthetic intent. But, then, cracks are not usually attractive in appearance.
Saturday, April 25, 2009
Purposeful chaos (the 2-minute design offense)
Mike (see Paint the Color Chip and Mike's Abridged Edition) offered another idea for managing labor costs on a design project. "If you know you are going to have to work overtime on a project," he said, "do it in the beginning. It costs less to do overtime when there are only one or two people working on a project."
Friday, April 24, 2009
Architectural Design: CAD doesn't care
Thursday, April 23, 2009
Masonry Construction: A hodgepodge of reinforcing
"He's almost done with it," the superintendent answered.
"Really? When did he start?" I asked.
"Yesterday," said the superintendent.
"Wow! I guess I'd better have a look," I said.
We walked around the end of the existing building to the location of the new gym, and, sure enough, the block back-up walls were full height, and the masons were installing brick veneer. I climbed the scaffolding to the level where the masons were working. Looking closely at the construction, I noticed that a variety of horizontal reinforcing had been used, and none of it was the type or dimension specified or approved through the submittal process. It was apparent that the masonry subcontractor had made use of a lot of scrap material left over from other projects. On the surface, the brickwork would look good, but the construction was clearly unacceptable. Although the masons had obviously invested a lot of effort in producing the work that was nearly complete, it would have to be redone.
As the architect, I could not direct the contractor to tear down the walls. Instead, I told the contractor's superintendent that I would not be able to approve any payment for the walls due to the use of incorrect reinforcing. The superintendent translated the message to the masonry subcontractor, who shouted obscenities at me but quickly took down the walls and soon rebuilt them with the correct reinforcing. The masonry work went very well on the rest of the project.
Masonry Design: A subtle difference in brick sizes
"Hey! Look at that small area of bricks with the fat mortar joints. What happened?"
Many U.S. buildings that are decades old were constructed of "standard" brick, each unit with an actual length of 8 inches. Today's "standard modular" brick of similar height and depth typically has a nominal length of 8 inches including the mortar head joint and an actual length of 7.625 inches, allowing for a .375 inch mortar head joint. (An actual length of 7.5 inches may also be available to accommodate a .5 inch head joint.) If you are renovating or adding to an existing brick building, it's a good idea to measure the existing brick. And, if you can't get a matching size, you may want to consider that in designing areas of infill.
(Similar issues can apply to matching existing brick color and bond. It may take a close look to spot a Flemish bond, a possible indication of underlying construction that differs from today's typical cavity wall or brick veneer construction.)
Tuesday, April 21, 2009
Productive coordination meetings on the go
Some of the most productive coordination meetings can take place when the architect goes to the consultants' offices. The consultants are on their own turf and may be more comfortable with the conversation. They may also have better access to coordination information and materials. Individual members of the consultant's team can be on call and participate only as needed, while continuing to be productive with other tasks in their office outside the meeting. A meeting in the consultant's office can be more economical for the consultant, and it can also be beneficial for the architect to see where and how the consultant's business is organized.
Sunday, April 19, 2009
Building Thermal Movement: Everything in a building moves
Sure, doors and windows may move, elevators and escalators go up and down, water runs through pipes, air through ducts, and fans turn on and off. But we tend to think of the structure, the walls, the floors, and the roof as fixed components that do not move. In fact, they all do move. They expand and contract at different rates in response to changes in temperature and/or humidity. Bricks and wood swell with moisture absorption; concrete shrinks as it cures; aluminum expands at a much higher rate than steel under the same temperature increase. Some movement is reversible; other movement is not. Much of this movement is imperceptible until the forces of expansion or contraction result in a visible scar like a crack in a wall or broken glass or water damage. Alas, the rewards for successfully accommodating building movement are not usually published.
Saturday, April 18, 2009
Value Engineering can add value
Friday, April 17, 2009
It takes timely money to make a project go
A different owner on a different project was not satisfied with the quality of part of the work done by the project's contractor, but chose to pay the contractor for that work anyway, hoping the contractor would correct it. Instead, the contractor proceeded with other work, making correction of the unsatisfactory work less practical and more costly. When the owner complained to the contractor about the contractor's failure to correct the unsatisfactory work, the contractor pointed out that the owner had paid for it, so the contractor considered it complete and thought the owner did, too. The following month, the owner withheld part of the contractor's payment to cover the cost of correcting the previous unsatisfactory work. Then construction progress was slowed by a delay in delivery of materials of approximately the same value as the payment amount withheld by the owner. The material supplier had furnished similar materials for several other projects done by the same contractor, and delivery for this project was contingent on the supplier's receipt of payment for a previous project.
During a very busy construction boom, a project owner decided to make advance payment to the project's contractor as an incentive to get construction started on his project. Then several weeks passed without any construction activity on the project. When the owner complained about the situation to a friend who had been a project owner during a previous recession, the friend told him he had done the same thing to help a contractor get that project started during the recession - and the result was the same.
It takes money to make a project go, but payment at the wrong time can be counterproductive.
Wednesday, April 15, 2009
So, you want to count trucks?
There are several problems with counting truckloads. First, of course, someone has to be present whenever the trucks are coming and going in order to count them ("Hey! No bathroom breaks!"). Then, the counter needs to be able to differentiate between a truck he has just seen and another one that is in the same vicinity ("Hey! That looks like the same truck. The driver just went around behind the building and came out again. That's cheating!"). In some cases the counter may need to determine how to consider material that is transferred from one truck to another truck or trucks ("Dude! That truck dumped its load on a pile over there, and the material was picked up and taken away by two other trucks. I counted 3. Should that really be 1? 2?"). Next come the questions about how much material is in the truck: "Is this a 7-yarder or a 10-yarder? Did you fill it even with the top of the dump box? Are the corners filled?" And, oh yeah, "How loose is the material? How should I determine a 'legitimate' cubic yard when I see all these spaces between the chunks in the truck?" What is the actual 'fluff' factor? And, finally, "This hole looks like it should have taken ten truckloads to remove the material, but I counted fifty! And it's looking like it will take 42 to fill it in."
These truck counting problems may be some of the reasons why authorities who establish such standards prefer to use 'in place' volume measurement to determine quantities.
But, hey, go ahead and count the trucks, if you want to. Don't forget to count that blue one over there. Is that coming or going?
The Schedule of Values deserves close attention
The meanings of the line items may seem simple enough at first glance, but they have been known to be interpreted differently by subcontractors, contractors, architects, engineers, and owners as construction proceeds. Site work items seem to be uniquely subject to varying interpretation. The intent of terms like "Excavation", "Cuts and Fills", "Fill", and others are good agenda items for a meeting to discuss a proposed Schedule of Values. For the architect and owner who will be assessing the value of periodic progress on a given item, it is especially important to understand what is included in the line item and what is not included - in part to avoid a possible disagreement as construction proceeds. "I think the owner already paid for that in this item," says the architect. "Oh, no," says the contractor or the sub. "That was never in that item. It was in this other item."
The architect's and owner's ability to assess progress on the listed work items also depends on the monetary amount of the particular item. It is common to require a contractor to break down items that are too large (e.g., Site Work $2,000,000) into smaller items (e.g., Rough Grade south yard: $15,000, Fine Grade west field: $7,500, etc.) that are more easily assessed and add up to the total value of site work. For some, the rule has been to break down the schedule into items no greater than $20,000 in value. That may not be a practical rule to follow in every case, but it is important to consider the ability of the observer to assess progress that is claimed on a given application for payment while avoiding confusion with other work that may be similar or within the same trade. Contractors and subcontractors are usually quite interested in receiving prompt payment for completed work, so it follows that they should be willing to invest time in the beginning of a project to establish a common understanding of the items in the Schedule of Values.
Another rule, sometimes challenged, is that once the Schedule of Values is established, it should not be changed. That's a good rule (with a notable exception that sometimes a more detailed breakdown of an established item may become necessary in order to assess progress and determine appropriate payment). And there are other rules....
Tuesday, April 14, 2009
Form suddenly meets function
When the program and related information arrived in the mail, the space planner went to work, and we also enlisted help from a cost estimator. The program information stressed the importance of the budget.
After several days, the space planner and the cost estimator met quietly with the boss. Then they both left the office, and the boss presented the rest of us with a dilemma.
The space planner had found that the program spaces could not fill the immense bow tie plan that the boss had created. All of the departments and their discrete spaces could be sprinkled along the perimeter wall of the bow tie plan at each floor, but that left a vast amount of unoccupied space in the interior of the building. The construction cost estimate exceeded the project budget severalfold. We were also running out of time; the submission deadline was only a few days away. We would have to abandon the bow tie, cut off part of it, or reduce it. Considering the boss's situation (and ours), we ruled out the first two options.
We determined an ideal efficiency for the building, and we photographically reduced a copy of the building perimeter plan by a percentage that would accommodate the program area at each floor while maintaining a high net to gross efficiency. Then we shuffled and fit the program areas into the reduced bow tie plan. It would not have been the best plan for building occupants and furnishings, but it was mathematically efficient. Also, the cost estimate shrank to fit the budget.
Alas, the firm's entry did not win. The entry's call for knocking down all adjacent buildings on the block - some apparently occupied by competition jurors - may have influenced the outcome and kept the bow tie design from receiving an award. However, there were stranger entries among the hundreds that found their way into the display tent. One, perhaps given more serious consideration, was a billboard-like building featuring a giant Marilyn Monroe.
Saturday, April 11, 2009
Pragmatism trumps engineering
The client company's engineers were not fazed by the cost information, but the client company's managers were more interested. A senior manager asked what loads were normally considered when designing a slab on grade for an industrial building, and the developer's engineer replied that 250 psf was a conservative norm. "That will be fine," replied the senior manager. And so it was.
Ask the right person or get the wrong answer
Wednesday, April 8, 2009
Monitoring construction progress
One effective way to monitor progress on a construction project is to consider cumulative payments to the contractor or claimed percent complete against an estimated payment schedule that should be established at the start of the project. In most cases the estimated schedule of cumulative payments or percent complete should look like an 'S' curve, similar to the one in the diagram above. It is likely to be relatively flat at start-up, due in part to the limited number of trades that can work on the project at first. As the project advances, progress allows the addition of trades (and workforce), indicated by the steeper line in the middle of the 'S' curve. The flatter tail end of the project represents a reduced workforce, fewer trades, finishing details, and punch-list work.
If actual progress looks much different than the 'S', the project may be headed for trouble. For example, a prolonged flat period at the beginning (or a shallower slope on the steeper part of the 'S' as shown by a dashed tangent line above) may forecast a late project completion. Alternatively, if requested payments suggest a steeper curve earlier in the project, the requested payments could be exaggerating actual progress, and one bad result could be releasing too much money too early and not holding enough funds to complete the project. The 'S' curve should not be considered an absolute measure of progress, but it can be an effective tool for comparison and forecasting.
[Note that a similar approach can be used for looking at design progress. See Staffing a design project.]
Staffing a design project
Managing staff level through the life of a design project is very important to a successful outcome. Staff levels should be increased gradually but early enough to allow for a project learning curve and also to allow for the tail end of the schedule to be spent tying up loose ends and putting the finishing touches on details (Curve A in the diagram above). A project staffing approach that follows Curve B in the diagram above suggests a combination of under-staffing and/or a need for a longer time-line.
[Another approach to this is to consider an 'S' curve, where the X axis is time (as in the diagram above), but the Y axis is cumulative staff hours or staff costs or percent complete. With that diagram, the steepest part of the 'S' should be in the middle of the diagram, and it should be close to flat at the beginning and at the end that represents project completion. This same 'S' curve approach can also be helpful in monitoring construction progress on a project. See Monitoring construction progress.]
Tuesday, April 7, 2009
Zero Slump Concrete
After a few of us had taken the architect license exam, we were talking about the questions. One of the multiple choice questions asked how long to wait before removing the cone during a concrete slump test. My colleague had chosen answer "c. 3 days".
Why we need to manage architectural projects
- "I already know what I'm going to do. Just tell me when to start."
- "I'm here to draw. I'm not interested in any program information."
- "I'm only going to do what I'm told, nothing else."
- "Finally, a chance to demonstrate my design prowess!"
- "I think we should use those windows that were presented to us at the last Lunch-n-Learn. Wasn't that a great tart?"
- "This is not a linear process. It takes as long as it takes."
- "I'm not going to let Jim ruin another project."
- "We never meet the budget, and we never finish on time. It's not my fault. That's just the way it is. Why can't you get that?"
- "Someone has to tell the owner to butt out. We already know what they need."
- "I don't mind attending a few meetings, but I'm not actually going to start doing any engineering work until I know the architect has stopped screwing around with the plan. I'm not getting enough fee to spend engineering time on design refinements."
- "We're going to do the whole project with our standard details."
- "Hey! It will be really cool if we tilt the walls over like this so they look like a roof but will still be made of wall materials. I wonder if it will keep the water out. Maybe it won't rain much. We can specify really good sealant. Maybe it will be okay this time."
- "Green? I'm not going to say it in these words out loud, but I refuse to be held accountable for any guinea pig design experiments or systems. Therefore, I'm going to do exactly the same thing I've done for the last 20 years. It's all going to be off the shelf. I don't want any call-backs on this project. That's what I call efficiency."
- "I will be calling all the shots. Period."
Monday, April 6, 2009
Saturday, April 4, 2009
Presenting the windows
"The mullions in Option B are about 1/16 inch wider than in Option A, and in Option C the horizontals are also 1/16 inch wider. We wanted to make sure you had a lot of choices. Do you have a preference?"
Friday, April 3, 2009
We usually locate the roof drains near the low point
We were working on the layout of the roof plan for a large, irregularly shaped building, designed with the structure gently warped to shed water to the edges. A drafter was adding roof drains to the plan, and I noticed that he was locating some of the drains about half way up the slope between the low point and the high elevation. I asked him why he was doing that, and he replied that he thought the drains at mid-slope would collect half the runoff on its way to the low point.
"Oh, I forgot to tell you," I said. "We usually locate the roof drains near the low point." He looked skeptical until I added, "It's office policy."
Thursday, April 2, 2009
A notable roof warranty exclusion
The 'sales rep' exclusion highlights a common dilemma. The manufacturer's sales rep typically has to please several "masters". The rep has to please the architect and project owner in order to get the manufacturer's product or system specified. Then the rep has to please the roofing contractor, the first-line customer who will actually purchase and pay the manufacturer (or distributor) for the product. And, of course, the rep has to please the manufacturer with productive sales. In construction, full payment usually follows installation, so the manufacturer's rep may be involved in site visits, inspections, and warranty processing related to project completion. In order to get paid upon project completion, the rep has to pursue the satisfaction of all these parties - the roofing contractor, the architect, the owner, the manufacturer, and maybe even a few others. That may be a tall order under circumstances where the interests of those parties are not all aligned, and one outcome may be a promise that cannot be kept. The 'sales rep' exclusion suggests that manufacturers have had experience with reps making promises that are contrary to the terms of a published warranty, and the exclusion protects the manufacturers from that problem.
Considering again the question "Who is the customer?", I recall a conversation with a manufacturer's rep several years ago. We were concerned with the quality of work that was being done by a roofing contractor, and we thought the manufacturer's rep might be able to help persuade the roofing contractor to do a better job. The rep's response to our request was very enlightening: "I can't really help you out with that," he said. "The roofing contractor is my customer."
Wednesday, April 1, 2009
Manage your consultants' communication with your client
"Oh, we did not realize you would be using a computer in the storage room," I said. I thought she had confused this storage room with her new office, which was located in another area.
"This is not a storage room," she replied. "It's my office. I told the kitchen consultant that I wanted this room to be my office. I did not want my office in the other area. He said he would take care of it."
When I looked at the food service equipment drawings, I realized the kitchen consultant really had changed this space from a storage room to an office, just as the Food Service Director requested. Unfortunately, he did not share the information about the request with anyone else, so the room had architectural, mechanical, and electrical features that were appropriate for storage use and not for office use.
Consultants should report back to the architect any owner requests to them for design changes. The changes could lead to other changes, and the overall costs and consequences may be such that the owner - once aware of them - would make a different decision. Consulting agreements can include provisions for reporting separate meetings and communications with the owner. It is also good practice to cover communication protocols in project kick-off meetings and to issue periodic reminders, especially when you are aware of a possible upcoming meeting between a consultant and a representative of your client. The clients may also benefit from reminders about communication protocols and communication channels for requesting changes.
Tuesday, March 31, 2009
Sunday, March 29, 2009
Project Coordination: Practice the Hand-off
Tailoring the delivery means delivering the message in a way that acknowledges and respects the ability of the listener to understand the message and make appropriate and productive use of it. A highly skilled and familiar employee may be able to hear an abbreviated message - maybe just a headline - and fill in the blanks with a good understanding of the desired or needed outcome. "Two over, rye, and a side," may be all the information that is needed in a situation where abbreviated communication has been developed through years of practice. In that case a lengthier description may be read as an insult - unnecessary micro-management. But a less skilled or less familiar employee may need more detail in order to make a connection with the message. In either case, immediate feedback can help to verify understanding of the message, and it may save a lot of time and money as a project goes forward. Familiarity is a key to the successful hand-off, because even a highly skilled new team member (employee, consultant, contractor, subcontractor, supplier, etc.) may bring a different understanding of the abbreviated message.
Friday, March 27, 2009
What's wrong with this picture?
a. The arrangement and swing of the door make the closet unusable, unless it is part of a set for a Three Stooges movie.
b. It was built as drawn, and it cost $1,000 to change the door to make the closet usable, because it was not part of a set for a Three Stooges movie.
c. The picture was not drawn in CAD.
d. 'a' and 'b' above.
Vinyl Composition Tile: Getting to the bottom of bumpy floor tile
Thursday, March 26, 2009
Missing consultant coordination, a hilltop building gets a surprise lift station
It would be better, if possible, for the engineers to coordinate their work so that the inside pipe and the outside pipe would meet at the same elevation. Apparently, someone did not understand that plumbing waste lines below the floor inside a building usually slope to drain, and that a run of a few hundred feet inside the building could put the waste pipe outlet several feet below the floor level, not just one foot, as suggested by the elevation at the end of the outside sewer pipe.
The person who presented the change order to the owner may have explained that it would be better to have a lift station, because you can't always count on gravity.
Wednesday, March 25, 2009
Roof Drainage Design: Early design decisions can influence roof and wall performance
It is possible for architectural designers to rely too much on technical details, specifications, and construction quality to overcome the challenges created by a design concept. A design concept can overwhelm the intended performance of roofs and walls that are expected to manage water and keep it out of a building’s interior. Where a roof slopes down toward or against a wall, the best flashing detail may simply not be up to the task of protecting the building from leaks. A roof configuration that includes numerous dormers and valleys, changing slopes and materials, and multiple levels can make drainage paths so convoluted or restricted that ice formations and leaks in snow country are almost inevitable. Roof design complexity also challenges effective ventilation of roof framing areas, especially in and around dormer and cathedral ceiling areas.
It’s interesting that popular features like dormers that mimic historic buildings can also bring problems like ice dams and leaks.
Avant-garde designs that tilt walls and rely on the wall materials to perform like roofs also risk performance shortcomings.
The best time to consider these possibilities and minimize risks is when the design is still in a formative stage.