Gaps between design disciplines are a common cause of construction
change orders. In some cases, the consulting disciplines' standard
practices may generate a gap. For example, the electrical engineer may
establish an electrical scope of work that "stops" 10 feet outside the
building, while the site civil engineer may expect (and indicate on the
site drawings) that the electrical contractor will provide power to a
sewage lift station that is 15 feet outside the building. Unfortunately,
it is quite possible that neither the electrical engineer nor the civil
engineer will become aware of this gap in electrical service until the
contractor submits an RFI.
Similar gaps can occur
between plumbing and site trades, between mechanical and general
building trades, between structural steel and miscellaneous metals
trades, and between other trades. In most cases, proactive coordination
by the project architect during the construction documents phase can
help to minimize these gaps."Proactive" coordination means getting
involved in finding and highlighting possible gaps and managing document
revisions to eliminate the gaps by conferring with the related
disciplines, considering applicable trade practices and regulations, and
assigning responsibility to the most appropriate party. (It's usually
not enough (and not really proactive) to simply tell the consultants to
work it out between themselves.)
Showing posts with label Site Work. Show all posts
Showing posts with label Site Work. Show all posts
Thursday, June 13, 2013
Tuesday, November 22, 2011
Planning for Concealed Site Conditions
Discovery of concealed site conditions can raise havoc with a project, possibly disrupting the construction schedule and adversely impacting the project budget. Here's a link to an article I wrote a few years ago to share some of my experience with concealed site conditions: Planning for Concealed Site Conditions
Wednesday, April 15, 2009
So, you want to count trucks?
It seems there is always a lively discussion about how to quantify additional earthwork on a project. While established standards may stipulate that payment will be based on compacted, 'in place' volume determined by survey, someone always wants to use a different method for determining quantities of material removed or imported, loose or compacted - and it seems there is always someone who wants to count truckloads.
There are several problems with counting truckloads. First, of course, someone has to be present whenever the trucks are coming and going in order to count them ("Hey! No bathroom breaks!"). Then, the counter needs to be able to differentiate between a truck he has just seen and another one that is in the same vicinity ("Hey! That looks like the same truck. The driver just went around behind the building and came out again. That's cheating!"). In some cases the counter may need to determine how to consider material that is transferred from one truck to another truck or trucks ("Dude! That truck dumped its load on a pile over there, and the material was picked up and taken away by two other trucks. I counted 3. Should that really be 1? 2?"). Next come the questions about how much material is in the truck: "Is this a 7-yarder or a 10-yarder? Did you fill it even with the top of the dump box? Are the corners filled?" And, oh yeah, "How loose is the material? How should I determine a 'legitimate' cubic yard when I see all these spaces between the chunks in the truck?" What is the actual 'fluff' factor? And, finally, "This hole looks like it should have taken ten truckloads to remove the material, but I counted fifty! And it's looking like it will take 42 to fill it in."
These truck counting problems may be some of the reasons why authorities who establish such standards prefer to use 'in place' volume measurement to determine quantities.
But, hey, go ahead and count the trucks, if you want to. Don't forget to count that blue one over there. Is that coming or going?
There are several problems with counting truckloads. First, of course, someone has to be present whenever the trucks are coming and going in order to count them ("Hey! No bathroom breaks!"). Then, the counter needs to be able to differentiate between a truck he has just seen and another one that is in the same vicinity ("Hey! That looks like the same truck. The driver just went around behind the building and came out again. That's cheating!"). In some cases the counter may need to determine how to consider material that is transferred from one truck to another truck or trucks ("Dude! That truck dumped its load on a pile over there, and the material was picked up and taken away by two other trucks. I counted 3. Should that really be 1? 2?"). Next come the questions about how much material is in the truck: "Is this a 7-yarder or a 10-yarder? Did you fill it even with the top of the dump box? Are the corners filled?" And, oh yeah, "How loose is the material? How should I determine a 'legitimate' cubic yard when I see all these spaces between the chunks in the truck?" What is the actual 'fluff' factor? And, finally, "This hole looks like it should have taken ten truckloads to remove the material, but I counted fifty! And it's looking like it will take 42 to fill it in."
These truck counting problems may be some of the reasons why authorities who establish such standards prefer to use 'in place' volume measurement to determine quantities.
But, hey, go ahead and count the trucks, if you want to. Don't forget to count that blue one over there. Is that coming or going?
Labels:
Construction Administration,
Site Work
Thursday, March 26, 2009
Missing consultant coordination, a hilltop building gets a surprise lift station
If you put a new building on a hilltop, the need for a sewage lift station may be the last thing you would expect. However, if you discover that the plumbing waste pipe leaving the building is below the end of the previously installed outside sewer pipe that goes to a newly constructed septic system, you may realize that gravity acting alone will not get the sewage into the septic tank. A sewage lift station - purchased through a change order - may be the most economical way to get the sewage to its intended destination.
It would be better, if possible, for the engineers to coordinate their work so that the inside pipe and the outside pipe would meet at the same elevation. Apparently, someone did not understand that plumbing waste lines below the floor inside a building usually slope to drain, and that a run of a few hundred feet inside the building could put the waste pipe outlet several feet below the floor level, not just one foot, as suggested by the elevation at the end of the outside sewer pipe.
The person who presented the change order to the owner may have explained that it would be better to have a lift station, because you can't always count on gravity.
It would be better, if possible, for the engineers to coordinate their work so that the inside pipe and the outside pipe would meet at the same elevation. Apparently, someone did not understand that plumbing waste lines below the floor inside a building usually slope to drain, and that a run of a few hundred feet inside the building could put the waste pipe outlet several feet below the floor level, not just one foot, as suggested by the elevation at the end of the outside sewer pipe.
The person who presented the change order to the owner may have explained that it would be better to have a lift station, because you can't always count on gravity.
Subscribe to:
Posts (Atom)